Scope Expansion - Shubenacadie
Postal Code Areas: B0N, B2S
Provider:
Bell Canada
Bell Canada
Technology:
Fibre to home/business
Fibre to home/business
Status:
Underway
Underway
Anticipated Completion:
January 2024*
January 2024*
* Estimated completion dates are based on best information available at this time and are subject to change.
Community notes:
- Nova Scotia Power scoping complete - 3 major grade 1 crossings affecting the schedule (including 2 railroad crossings).
- As of March 2024, 64 out of 89 civic addresses remain.
- Individual addresses often have access before project area is complete.
- Addresses with access to date will be posted here, as available.
- If your location is in the red zone, off a blue road and serviced by power lines, you’re expected to be served.
- Please check for Satellite Internet Service Rebate Program eligibility as an interim solution and learn more here.
Communities included:
McLennan Brook, Milford, McDonald Rd, Moxsom Rd, Crombe Rd
Information last updated: March 2024